Main North Road optimisation

Objective

Corridor optimisation

Client

Christchurch Transport Operations Centre (CTOC)

Location

Christchurch

Deliverable

Report

Timeframe

Dec 2013 - Feb 2020

Project Status

Complete

Background

In order to optimise the function and safety of the route by mode and time of day, ViaStrada and Aurecon conducted site audits at eight intersections; researched the planning and engineering context; identified capacity constraints; analysed crash data and safety issues, considered modal requirements; identified engineering and operational improvements with costings.